Construction Update – May 2024


According to the City of Madison Department of Engineering staff, renovations for the Madison Public Market are proceeding on time and without unexpected surprises. At this time, 99% of concrete work has been completed, which involved removing and replacing the cement floors throughout the 45,000 sq. ft. building. The floors needed to be removed to accommodate plumbing, sewer lines and other essential components. Daniels Construction has completed the elevator shaft (first floor to mezzanine), and the back lot is now ready for re-paving. We are still on track for an opening in early Summer, 2025.

The Madison area has many amazing facets, but nothing quite like the public market. I can’t wait to watch this community hub come to life and foster small business growth and diverse connections! - Rebecca Prochaska, Potter Lawson

See What People are Saying